CURRICULUM

Eight modules. One coherent system.

Each module addresses a specific failure mode that recurs on hyperscale builds. Together they form a complete operating framework — from the first preconstruction decision to the last lesson captured at turnover.

Modules are available free with email signup. No course platform, no subscription — just the content.

01

Delivery mode determines everything

Self-directed CM vs. owner-side oversight under EPC/GMP — how to identify which you're in and what changes. The PM's role, authority, and risk exposure are fundamentally different in each. Most PMs don't know which mode they're in until something goes wrong.

CM at-risk vs. EPC contract structures
Owner's-rep authority and limits
What changes when you're on the owner's side
How delivery mode affects change control and risk allocation
Delivery Mode Identification Checklist
02

The handoff gate

What execution must inherit from preconstruction — scope, AACE-classed estimate, L2 schedule, procurement log, risk register, Cx framework — and why mobilizing without it is the first mistake. The gate is a set of deliverables, not a meeting.

Six required gate deliverables
How to assess gate readiness
What to do when the gate isn't ready but pressure to mobilize is real
Design-freeze as a cost control mechanism
Preconstruction Handoff Checklist
03

Procurement is the schedule

Long-lead release milestones, lead time starts at submittal approval, decoupling hardware POs from install awards. On a hyperscale build, the procurement log is the schedule — everything else is sequenced around it.

Long-lead identification and release milestones
Submittal approval as lead-time start
Decoupling equipment POs from install contracts
Procurement log as the critical path document
Long-Lead Procurement Tracking Template
04

Estimate classification and contingency

AACE 18R-97/56R-08 estimate classes, calculated contingency per 40R-08, and $/MW sanity checks. Most hyperscale projects carry the wrong contingency for the wrong reasons — this module fixes that.

AACE Class 1–5 definitions and appropriate use
Calculated vs. factored contingency (40R-08)
$/MW benchmarks and how to use them
When to escalate estimate class before proceeding
Estimate Classification Reference Card
05

Schedule integrity

Stale forecasts vs. red forecasts, defending the last milestone (turnover) separately, why later phases slip 2–4x the first. A schedule that isn't updated is a lie — and a lie that compounds.

The difference between a stale forecast and a red forecast
Defending turnover as a separate milestone
Why early-phase slippage multiplies
How to maintain CPM integrity under delivery pressure
Schedule Health Assessment Checklist
06

Change control

Schedule impact on every CO, CPM fragnet or no claim, why most change is owner/design-driven and what that means for design freeze. Change control is not paperwork — it is the mechanism that keeps the contract honest.

Schedule impact analysis on every change order
CPM fragnet requirements for time claims
Owner- and design-driven change patterns
Design freeze as a change control tool
Change Order Impact Analysis Template
07

Commissioning by design

Levels 1–5, safety floor never sampled, find every defect at the cheapest place to fix it, first-article gates. Commissioning is not a phase — it is a framework designed from day one and executed throughout construction.

Commissioning Levels 1–5 defined
Safety floor: what cannot be sampled
First-article gates and what they reveal
Cx framework as a preconstruction deliverable
Commissioning Readiness Gate Checklist
08

Lessons that compound

Real-time capture, the feedback flywheel, why a lesson recurring at a second site is a mechanism failure. The value of lessons learned is zero if they aren't captured in real time and closed before the next build starts.

Real-time vs. retrospective capture
The feedback flywheel: from lesson to mechanism change
Fleet-level lessons and what they reveal about systems
Why recurring lessons are mechanism failures, not bad luck
Lessons Capture Framework Template

Start with Module 01.

Enter your email to access the full curriculum. You'll also receive the Preconstruction Handoff Checklist — the most-used single document from this framework.